Project settings has two pages: Project and Impact calculation. Open Settings from the menu under your name. The settings sidebar lists both pages under the project they edit. The project menu in the header switches to another project, or to All projects to change every project at once.
The Impact calculation settings change the results of the whole project, so settle them before you report. Change on the Impacts Method tab opens them too.
Project
Here you edit the project's name, description, and reporting period. They don't change results. See Projects.
Impact calculation
These settings decide which data and choices go into your results. The page groups them in three sections:
- Releases are the factor set and the sector matching release the project uses. Your results change only when you update one, which recalculates the project.
- Factors decide which default factors Nios uses. Changing one recalculates the project.
- Results decide how results are combined and shown. A change applies at once, without a recalculation.
| Section | Setting | Default | What it changes |
|---|---|---|---|
| Releases | Factor set | Latest when the project was created | The factor data and calculation method behind every result |
| Releases | Sector matching | Latest | How Nios finds base sectors |
| Factors | Metrics | All 17, on EXIOBASE 200 | Which metrics the project calculates, and the classification system each metric's sectors come from |
| Factors | Outlier treatment | On | Caps extreme default factor values |
| Factors | Price basis conversion | Off | Converts purchaser-price spend to the basic prices the factors use |
| Results | Ecosystem weighting | Off | Weights terrestrial, freshwater, and marine impacts in the Nature total |
| Results | Base currency | EUR | Currency of spend and intensities |
A recalculation runs in the background for the whole project. The status bar on Activities shows its progress.
All projects
With All projects in the header's project menu, Impact calculation shows each setting across every project in your organization. Where projects differ, an amber icon follows the setting's name. Click it to see which projects use which value, for example EUR for three projects and USD for one.
A setting whose projects differ shows that in its control: a checkbox or switch shows a dash, and a select or a metric count reads Mixed. Click it to choose one value for all projects. A metric category's select can also read Mixed because its metrics use different classification systems, see Metrics. Only the amber icon means the projects differ.
A change saves at once to every project that had another value, for example "Outlier treatment turned on in 3 projects". Undo in the message reverts it. A change to factors recalculates the projects it changed.
Update all projects on Factor set or Sector matching updates every project that is behind, also where someone chose Not now.
Factor set
The factor set is the factor data and calculation method behind your results, for example factor set 1.1 with GLORIA v059a, EXIOBASE v3.10.1, and LC-Impact v1.3. A project keeps its factor set until you update it, so a number you reported stays reproducible. New projects start on the latest one.
When a newer factor set ships, the row reads, for example, "Factor set 1.2 is available." Update recalculates every activity with the new data and method, so totals can change. Base sectors and metric sectors stay. What's new opens its changelog entry.
Export your results before you update if you need the old numbers. See Results and export.
Sector matching
A sector matching release decides how Nios finds base sectors. New activities always match with the latest release. Activities matched earlier keep their base sectors until you update, so your results don't change by themselves.
When activities were matched with an older release, the row says how many. Show activities opens Activities filtered to Matching version: older. Update matches them again and recalculates the project. Base sectors you selected or confirmed stay.
Example: Sector matching 1.1 improves bakery products. Your 12 bakery activities keep their base sectors until you click Update.
Updates when you open a project
When a newer release ships, opening the project shows "New releases for this project" with a line for each release that says what it brings. Update project takes all of them and recalculates the project once. Its menu updates one release, or all projects. Not now hides the message until the next release, and the settings keep offering the update.
Anyone who can edit the project's activities can update it.
Metrics
A project calculates the metrics you check. They're grouped by the pressure categories of the Impacts page: Ecosystem Use, Climate Change, Pollution, and Resource Exploitation. Uncheck the categories you don't report, for example everything but Climate Change for a climate-only project. A category's count, such as 5 of 5, opens its metrics for a finer choice. Climate Change holds only GHG emissions, which also feeds the Climate lens, so unchecking it removes that lens too.
An unchecked metric gets no results: Activities and the spreadsheet template hide its column, its cells raise no issues, and Impacts leaves it out. It also drops out of what an activity needs to be calculated, see What Nios needs. Your data in it stays, so checking the metric again brings back its cells and impact inputs.
A Nature total over fewer metrics is smaller than one over all 17. When you compare two projects that calculate different metrics, the comparison says so. The Method tab shows how many metrics a project calculates.
Each checked metric takes its metric sectors from one classification system, so its results rest on one factor dataset across the project:
- EXIOBASE 200: 200 products. The default for every metric except intensive forestry.
- GLORIA 120: 120 economic sectors. The default for intensive forestry, which EXIOBASE has no factors for.
A category's select sets all its metrics, and a metric's select sets just that one. Only metrics with factors in the chosen system switch. A category whose metrics use different classification systems reads Mixed, as Ecosystem Use does by default.
Example: Select GLORIA 120 for Pollution. The 4 acidification and ozone metrics switch, the 5 eutrophication metrics stay on EXIOBASE 200, because GLORIA has no factors for them, and Pollution shows Mixed.
Metric cells accept only the metric's classification system, besides impact inputs. A sector from another system shows "Classification system not allowed for this metric".
Changing the setting recalculates the project. Base sectors stay as they are.
Outlier treatment
Input-output tables contain a few sector and country factors that are extreme, often because the source data for that combination is small or noisy. With outlier treatment on, Nios caps a factor that falls in the top or bottom 1% of values, but only when it's extreme both within its sector and across all sectors.
Outlier treatment applies to default factors only. Your impact inputs are never capped. Turn it off if you need to reproduce raw GLORIA or EXIOBASE values. See Methodology for the method.
Price basis conversion
Default factors are per euro at basic prices, what the producer receives. Most spend data is at purchaser prices, with taxes and margins on top, so results from it run high. With price basis conversion on, Nios converts every activity whose Price type is Purchaser to basic prices before the factor applies. For example, EUR 100 of food products from Finland becomes EUR 84.5.
The conversion clears the "Review price type" warning on every row it converts. The warning stays where no share exists for the metric sector and country, and where the price type is Unknown or blank. The activity's conversion hover shows the share and where it came from, including when it's an average rather than observed for the country. Your impact inputs are never converted. See Methodology for the method.
Ecosystem weighting
With weighting off, Nios adds the terrestrial, freshwater, and marine biodiversity impacts, each counting fully. Turn it on to weight them by importance instead: Nios multiplies each ecosystem's impact by its weight before adding them.
The weights start at 0.34, 0.33, and 0.33 and must add up to 1.00, with up to three decimals. Because the weights add up to 1, the weighted total is an average of the three ecosystems, so Nature totals become much smaller than with weighting off.
Example: El Geneidy et al. (2026) propose 0.801 for terrestrial, 0.096 for freshwater, and 0.102 for marine. Nios accepts it because the sum, 0.999, is within rounding.
Weighting is a value choice. LC-Impact recommends reporting the three ecosystems separately unless you weight them deliberately. Note whether you weighted, and with which weights, when you share results.
Base currency